Reconstruction of a high clayey railway embankment using piles (CROSBI ID 512848)
Prilog sa skupa u zborniku | izvorni znanstveni rad | međunarodna recenzija
Podaci o odgovornosti
Goluža, D. ; Vukadinović, Bojan ; Kvasnička, Predrag
engleski
Reconstruction of a high clayey railway embankment using piles
This paper describes three possible solutions for reconstructing the railway embankment on the railway line between Zagreb and Rijeka. For this purpose, site investigations and laboratory tests were carried out to obtain characteristic values of parameters necessary for embankment stability calculations. Of the three solutions considered, only the solution involving the use of piles requires no railway traffic disruptions. Therefore, possible pile lengths were analysed to found out that a factor of safety sharply increased as the pile length was increased from 8 up to 12 metres.
railway embankment; reconstruction; stability
nije evidentirano
nije evidentirano
nije evidentirano
nije evidentirano
nije evidentirano
nije evidentirano
Podaci o prilogu
159 -163-x.
2005.
objavljeno
Podaci o matičnoj publikaciji
Proc. Conf . Soil-Structure interaction: Calculation methods and engineering practice. Sankt Petersburg
Ulitsky V.M.
Sankt Peterburg: ASV Publishers
Podaci o skupu
Soil-Structure interaction: Calculation methods and engineering practice. Sankt Petersburg
predavanje
26.05.2005-28.05.2005
Sankt Peterburg, Ruska Federacija