Nalazite se na CroRIS probnoj okolini. Ovdje evidentirani podaci neće biti pohranjeni u Informacijskom sustavu znanosti RH. Ako je ovo greška, CroRIS produkcijskoj okolini moguće je pristupi putem poveznice www.croris.hr
izvor podataka: crosbi !

Analysis of the retention embankment of the hydro-power plant basin (CROSBI ID 538226)

Prilog sa skupa u zborniku | ostalo | međunarodna recenzija

Mulabdić, Mensur ; Petrović, Nikifor ; Minažek, Krunoslav Analysis of the retention embankment of the hydro-power plant basin // Proceedings, 12th International Symposium of MASE, Struga, Macedonia. 2008

Podaci o odgovornosti

Mulabdić, Mensur ; Petrović, Nikifor ; Minažek, Krunoslav

engleski

Analysis of the retention embankment of the hydro-power plant basin

Retention basin for the future hydro-power plant was designed to be controlled by the embankments along the river. The length of the embankment is about 20 km while the height of the embankments was chosen to be about 5, 5 m. The embankment geometry and structure were subject of the analyses in terms of the soil materials at disposition, filter position, erosion protection and loss of water due to seepage bellow and through the embankment. Based on available geotechnical data and demands put on the embankment, the extensive analytical analyses were conducted on different embankment geometries simulating influence of the specific site conditions in the foundation, presence and depth of impermeable wall, shape and distance of a drainage canal at the embankment toe. The foundation soils consisted of very thin clayey material at the surface overlaying sand to depths of more than 40 m. Of special importance was embankment stability under earthquake loadings as the area has high seismic risk and the sand in the foundation is prone to liquefaction. Finally, based on the analyses embankment slope angles were suggested, position and shape of the filter layers were chosen and additional investigation work was proposed for further analysis of the liquefaction potential. The article will demonstrate criteria put on materials, embankment structure and foundation in order to satisfy project needs.

embankment; seepage; stability; earthquake; filter; analyses

nije evidentirano

nije evidentirano

nije evidentirano

nije evidentirano

nije evidentirano

nije evidentirano

Podaci o prilogu

2008.

objavljeno

Podaci o matičnoj publikaciji

Proceedings, 12th International Symposium of MASE, Struga, Macedonia

Podaci o skupu

Nepoznat skup

ostalo

29.02.1904-29.02.2096

Povezanost rada

Građevinarstvo